114 Whitwell Street Community Update October 16th

114 Whitwell Street Community Update October 16th

Dear Neighbors,   As noted last week, we’ve reached the point in the project where we will be extending construction activities to Saturdays. Saturday work will continue on a regular basis throughout the duration of the project.   A brief update for Saturday,...
114 Whitwell Street Community Update October 9

114 Whitwell Street Community Update October 9

Dear Neighbors,     We’ve reached the point in the project where we will be extending construction activities to Saturdays, which is expected to continue on a regular basis throughout the duration of the project.   A brief update for Saturday, October 9: The...
114 Whitwell Street Community Update October 4th

114 Whitwell Street Community Update October 4th

Dear Neighbors,   A brief update for the week of October 4th: We anticipate Building B foundation excavation to be complete within the next two weeks The foundation walls for Building B are ongoing The jackhammering of the ledge was finished on 9/28 to make way for...
114 Whitwell Street Community Update September 27, 2021

114 Whitwell Street Community Update September 27, 2021

Dear Neighbors,   A brief project update for the week of September 27th: The team is nearing completion on the jackhammering of the ledge that was discovered onsite. Our team will send a follow up as soon as the work is complete — the current expectation is early in...
114 Whitwell Street Community Update September 20, 2021

114 Whitwell Street Community Update September 20, 2021

Dear Neighbors,   A brief project update for the week of September 20th: Removal of the Admin. building concrete pad was completed last week Building B’s foundation excavation is approximately 80% complete Building B foundation wall construction is ongoing We...