Dear Neighbors:

A brief update for April 6, 2024:

  • There will be contractors on site on Saturday, April 6, 2024

Construction Updates:

Site Work

  • Site work is anticipated to be completed in June

Building C

  • Finishes are ongoing
  • Countertops and cabinetry installation are ongoing
  • First move-ins are expected in early June

Glendale Park:

  • Concrete sidewalks have been poured 
  • Parking space paving is tentatively scheduled for the end of April or beginning of May
  • Landscaping improvements will take place in the coming weeks, weather dependent