Dear Neighbors:
A brief update for February 3rd:
- There will be contractors on site on Saturday, February 3rd
Construction Updates:
Site Work
- Concrete steps and ramps around building D are ongoing
- Site work continues around buildings C & D
Building C
- Finishes are ongoing
- Countertops and cabinetry installation is underway
Building D
- Final inspections are underway
Glendale Park:
- Weather conditions have delayed work in Glendale Park, but it is anticipated that this work will begin shortly – more details will be sent out as they are available
- Removal of stumps from the trees that had previously been cut down
- Removal of old curbing and installation of new curbing
- Minor site work to prepare for sidewalks