Dear Neighbors:
A brief update for January 20th:
- There will be contractors on site on Saturday, January 20th
Construction Updates:
On Tuesday, January 23rd, there will be work at the end of Euclid Avenue adjacent to the property to reduce runoff onto Euclid Ave, Glendale Park, and adjacent properties:
- The work will include concrete cutting and site work beginning at 7am
Site Work
- Concrete steps and ramps around building D are ongoing
- Site work continues around buildings C & D
Building C
- Finishes are ongoing
- Countertops and cabinetry installation is underway
Building D
- Lobby finishes are now complete
- Finishes on levels 1-6 are now complete
Glendale Park:
- Weather conditions have delayed work in Glendale Park, but it is anticipated that this work will begin the week of 1/22:
- Removal of stumps from the trees that had previously been cut down
- Removal of old curbing and installation of new curbing
- Minor site work to prepare for sidewalks