Dear Neighbors:

A brief update for December 9th:

  • There will be contractors on site on Saturday, December 9th
  • Please note that we are moving to bi-weekly updates

Construction Updates:

Site Work

  • Sidewalks on site are being installed 
  • Courtyard irrigation and planting has been completed

Building C

  • Metal panel façade is now complete
  • Finishes are ongoing
  • Countertops and cabinetry installation is underway

Building D

  • Drywall installation is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is now complete
  • Finishes on levels 1-6 are nearing completion
  • GWB and paint is now complete
  • Installation of stairs on North side of building is underway

Glendale Park

  • Work at Glendale Park is currently on hold