Dear Neighbors:

A brief update for November 22nd:

  • There will be no contractors on site on Thursday, November 23rd
  • The site will be open in a limited capacity on Friday (November 24th) and Saturday (November 25th)
  • Please note that we are moving to bi-weekly updates

Construction Updates:

Site Work

  • Sidewalks on site are being installed 
  • Planting and irrigation install continues

Building C

  • Metal panel façade is in progress
  • Finishes are ongoing
  • Countertops and cabinetry installation is underway

Building D

  • Drywall installation is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is ongoing
  • Finishes on levels 1-6 are nearing completion
  • GWB and paint is ongoing

Glendale Park

  • Work in Glendale Park is expected to resume on the week of November 27th, weather dependent
  • The remainder of the path and site work is planned for that week, and will include:
  • Grading and installation of timber stairs along path
  • Curbing & signage installation
  • Completion of parking spaces & concrete walkways – concrete pouring, paving and striping (substantially complete)