Dear Neighbors:
Dear Neighbors:
A brief update for October 14th:
- The contractor will be on-site Saturday, October 14th
- Please note that we will be moving to bi-weekly updates after this week
Construction Updates:
Site Work
- Courtyard waterproofing and landscaping is ongoing
- Sidewalks on site are being installed
- Planting and irrigation install continues
- Open space improvements at Glendale Park are ongoing
Building C
- Metal panel façade is in progress
- Interior rough is ongoing
- Finishes are ongoing
Building D
- Drywall installation is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Interior doors and frame installation is ongoing
- Finishes on levels 1-6 are nearing completion
- GWB and paint is now underway on lower level