A brief update for September 16th:

  • The contractor will be on-site Saturday, September 16th

Construction Updates:

Site Work

  • Courtyard waterproofing and landscaping is ongoing
  • Sidewalks on site are being installed
  • Planting and irrigation install continues
  • Open space improvements at Glendale Park are ongoing

Building B

  • We received Certificate of Occupancy
  • Residents are in the process of moving in

Building C

  • Window installation is complete
  • Masonry façade is complete
  • Metal panel façade is in progress
  • Interior rough is ongoing
  • Finishes are ongoing

Building D

  • Drywall installation is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is ongoing
  • Countertops are ongoing