Dear Neighbors:

A brief update for August 5th:

  • The contractor will be on site Saturday, August 5th

Construction Updates:

Site Work

  • Courtyard waterproofing and landscaping is ongoing
  • Sidewalks on site are being installed
  • Planting and irrigation install continues

Building B

  • Interior painting is ongoing
  • Cabinetry and finish work is ongoing
  • Countertops are underway
  • Appliance install continues through the lower portion of the building

Building C

  • Window installation is ongoing
  • Masonry and metal panel is ongoing
  • Interior rough is ongoing

Building D

  • Internal fire protection, plumbing, HVAC, and electrical are ongoing
  • Drywall installation is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is ongoing
  • Countertops are ongoing