A brief update for May 27th:

  • The contractor will be on site Saturday, May 27th

Construction Updates:

Site Work

  • Courtyard waterproofing and landscaping is ongoing
  • Sidewalks on site are being installed

Building A

  • Interior painting is ongoing
  • Corridor finishes are underway
  • Lobby finishes are nearing completion

Building B

  • Interior painting is ongoing
  • Cabinetry and finish work is ongoing
  • Countertops are underway

Building C

  • Air vapor barrier installation is nearing completion
  • Roofing is ongoing
  • Window installation is ongoing
  • Masonry is ongoing

Building D

  • Internal fire protection, plumbing, HVAC, and electrical are ongoing
  • Drywall installation is ongoing
  • Gypcrete flooring is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is ongoing
  • Exterior facade masonry is ongoing
  • Countertops are ongoing

Admin Building

  • Fire protection, HVAC, plumbing and electrical are nearing completion
  • Painting is ongoing
  • Elevator installation is ongoing
  • Site improvements around the building are ongoing
  • Millwork and tile installation are ongoing
  • Gym addition cladding is nearing completion