Dear Neighbors:
A brief update for April 8th:
- The contractor will be on site Saturday, April 8th
Construction Updates:
Site Work
- Courtyard waterproofing and landscaping is ongoing
- Sidewalks on site are being installed
Building A
- Interior painting is ongoing
- Elevator installation is now complete
- Corridor finishes are underway
- Carpeting is nearing completion
Building B
- Exterior facade masonry is nearing completion
- Interior painting is ongoing
- Cabinetry and finish work is ongoing
- Countertops are underway
Building C
- Air vapor barrier installation is ongoing
- Roofing is underway
- Window installation is underway
Building D
- Internal fire protection, plumbing, HVAC, and electrical are ongoing
- Drywall installation is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Interior doors and frame installation is ongoing
- Exterior facade masonry is ongoing
- Countertops are underway
Admin Building
- Fire protection, HVAC, plumbing and electrical are nearing completion
- Drywall installation is nearing completion
- Painting is underway
- Elevator installation is underway
- Site improvements around the building are underway
- Millwork and tile installation are now underway