Dear Neighbors:
A brief update for March 25th:
- The contractor will be on site Saturday, March 25th
Construction Updates:
Site Work
- Courtyard waterproofing and landscaping is ongoing
- Sidewalks on site are being installed
Building A
- Interior painting is ongoing
- Elevator installation is now complete
- Corridor finishes are underway
- Carpeting is expected to begin at the end of the month
Building B
- Exterior facade masonry is nearing completion
- Interior painting is ongoing
- Cabinetry and finish work is ongoing
- Countertops are underway
Building C
- Air vapor barrier installation is ongoing
- Roofing is underway
- Window installation is underway
Building D
- Internal fire protection, plumbing, HVAC, and electrical are ongoing
- Drywall installation is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Interior doors and frame installation is ongoing
- Exterior facade masonry is ongoing
- Countertops are underway
Admin Building
- Fire protection, HVAC, plumbing and electrical are nearing completion
- Drywall installation is nearing completion
- Painting is underway
- Elevator installation is underway
- Site improvements around the building are underway
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.