Dear Neighbors:

A brief update for March 11th:

  • The contractor will be on site Saturday, March 11th

Construction Updates:

Site Work

  • Courtyard waterproofing and landscaping is ongoing
  • Sidewalks on site are being installed 

Building A

  • Interior painting is ongoing
  • Elevator installation is underway
  • Corridor finishes are underway

Building B

  • Internal plumbing, fire protection, HVAC, electrical and insulation are complete
  • Exterior facade masonry is nearing completion
  • Drywall installation is complete
  • Interior painting is ongoing
  • Gypcrete flooring is complete
  • Cabinetry and finish work is ongoing through 3rd floor
  • Countertops on floor 2 going in next week

Building C

  • Wood framing is ongoing
  • Air vapor barrier installation is ongoing
  • Roofing is expected to begin within the next two weeks

Building D

  • Internal fire protection, plumbing, HVAC, and electrical are ongoing
  • Drywall installation is ongoing
  • Gypcrete flooring is ongoing
  • Bathroom and kitchen cabinet installation is ongoing
  • Interior doors and frame installation is ongoing
  • Exterior facade masonry is ongoing
  • Countertops on 5th floor are underway

Admin Building

  • Fire protection, HVAC, plumbing and electrical are nearing completion
  • Drywall installation is nearing completion
  • Painting is expected to start next week
  • Elevator installation is underway
  • Site improvements around the building are underway

For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.

 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.