Dear Neighbors:

A brief update for February 25th:

  • The contractor will be on site Saturday, February 25th

Construction Updates:

  • Site Work
    • Courtyard waterproofing and landscaping is ongoing
    • Sidewalks on site are being installed 
  • Building A
    • Interior painting is ongoing
    • Appliance installation is now complete
    • Elevator installation is underway
  • Building B
    • Internal plumbing, fire protection, HVAC, electrical and insulation are complete
    • Exterior facade masonry is nearing completion
    • Drywall installation is expected to be complete this week
    • Interior painting is ongoing
    • Gypcrete flooring is expected to be complete next week
    • Cabinetry and finish work is ongoing
  • Building C
    • Wood framing is ongoing
  • Building D
    • Internal fire protection, plumbing, HVAC, and electrical are ongoing
    • Drywall installation is ongoing
    • Gypcrete flooring is ongoing
    • Bathroom and kitchen cabinet installation has begun
    • Interior doors and frame installation has begun
    • Exterior facade masonry is ongoing
  • Admin Building
    • Fire protection, HVAC, plumbing and electrical are nearing completion
    • Drywall installation is nearing completion
    • Elevator installation is underway
    • Site improvements around the building are underway

For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.

 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.