Dear Neighbors:
A correction on the hours for December 31 – January 2:
- The contractor will be on site Saturday, December 31st
- The site will be open Monday, January 2nd
Construction Updates:
- Building A
- Exterior façade masonry is expected to be completed this week
- Interior painting is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Bathroom tile installation is ongoing
- Interior doors and frame installation is ongoing
- Appliance installation is underway
- Building B
- Internal plumbing, fire protection, HVAC, electrical and insulation are ongoing
- Exterior facade masonry is ongoing
- Drywall installation is ongoing
- Interior painting is ongoing
- Cabinetry and finish work is underway
- Building C
- Wood framing is ongoing
- Building D
- Internal fire protection, plumbing, HVAC, and electrical are ongoing
- Drywall installation is ongoing
- Admin Building
- Interior framing is now complete
- Window installation is now complete
- Fire protection, HVAC, plumbing and electrical are ongoing
- Drywall installation is now underway
- Elevator installation is underway
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.