A brief update for December 17th:

  • The contractor will be on site on Saturday, December 17th

Construction Updates:

  • Building A
    • Exterior façade masonry is nearing completion
    • Interior priming and painting is ongoing
    • Gypcrete flooring is ongoing
    • Bathroom and kitchen cabinet installation is ongoing
    • Bathroom tile installation is ongoing 
    • Interior doors and frame installation is ongoing
    • Appliance installation has begun
  • Building B
    • Internal plumbing, fire protection, HVAC, electrical and insulation are ongoing
    • Exterior facade masonry is ongoing
    • Drywall installation is ongoing
    • Interior priming and painting have begun
    • Cabinetry and finish work has now begun
  • Building C
    • Underground plumbing is was completed on 12/12
    • Wood framing is ongoing
    • Slab concrete is expected to be complete next week
  • Building D
    • Internal fire protection, plumbing, HVAC, and electrical are ongoing
    • Drywall installation is ongoing
  • Admin Building
    • Interior framing is now complete
    • Window installation is now complete
    • Fire protection, HVAC, plumbing and electrical are ongoing
    • Drywall installation is expected to begin 12/21

For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.

 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 