Dear Neighbors:
A brief update for December 17th:
- The contractor will be on site on Saturday, December 17th
Construction Updates:
- Building A
- Exterior façade masonry is nearing completion
- Interior priming and painting is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Bathroom tile installation is ongoing
- Interior doors and frame installation is ongoing
- Appliance installation has begun
- Building B
- Internal plumbing, fire protection, HVAC, electrical and insulation are ongoing
- Exterior facade masonry is ongoing
- Drywall installation is ongoing
- Interior priming and painting have begun
- Cabinetry and finish work has now begun
- Building C
- Underground plumbing is was completed on 12/12
- Wood framing is ongoing
- Slab concrete is expected to be complete next week
- Building D
- Internal fire protection, plumbing, HVAC, and electrical are ongoing
- Drywall installation is ongoing
- Admin Building
- Interior framing is now complete
- Window installation is now complete
- Fire protection, HVAC, plumbing and electrical are ongoing
- Drywall installation is expected to begin 12/21
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.