Dear Neighbors:
A brief update for November 19-26:
- The contractor will be on site on Saturday, November 19th
- The site will be closed on Thursday, November 24th for the holiday and will reopen on Friday, November 25th
- The contractor will be on site on Saturday, November 26th
Construction Updates:
- Building A
- Exterior façade masonry is ongoing
- Drywall installation is expected to be complete by the end of the month
- Interior priming and painting is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Bathroom tile installation is ongoing
- Interior doors and frame installation is ongoing
- Building B
- Internal plumbing, fire protection, HVAC, electrical and insulation are ongoing
- Exterior facade masonry is ongoing
- Drywall installation is ongoing
- Interior priming and painting have begun
- Building C
- Underground plumbing is ongoing
- Building D
- Internal fire protection, plumbing, HVAC, and electrical are ongoing
- Window installation is ongoing
- Drywall installation is ongoing
- Admin Building
- Interior framing is ongoing
- Window installation is ongoing
- Fire protection, HVAC, plumbing and electrical are ongoing
- Roofing is ongoing
- Site Work:
- The soil stockpile was relocated to the western side of the site to allow for the installation of work in its former location. The soil will be used for backfill against Buildings C and D at a later date.
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.