Dear Neighbors:
A brief update for November 12th:
- The contractor will be on site on Saturday, November 12th
Construction Updates:
- Building A
- Exterior façade masonry is ongoing
- Drywall installation is ongoing
- Interior priming and painting is ongoing
- Gypcrete flooring is ongoing
- Bathroom and kitchen cabinet installation is ongoing
- Bathroom tile installation is ongoing
- Interior doors and frame installation is ongoing
- Building B
- Internal plumbing, fire protection, HVAC, electrical and insulation are ongoing
- Exterior facade masonry is ongoing
- Drywall installation is ongoing
- Interior priming and painting have begun
- Building C
- Underground plumbing is ongoing
- Elevator shaft construction was completed 10/28
- Building D
- Internal fire protection is ongoing
- Window installation is ongoing
- Drywall installation has begun
- Admin Building
- Interior framing is ongoing
- Window installation is ongoing
- Fire protection, HVAC, plumbing and electrical have begun
- Roofing is ongoing
- Site Work:
- The soil stockpile was relocated to the western side of the site to allow for the installation of work in its former location. The soil will be used for backfill against Buildings C and D at a later date.
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.