Dear Neighbors:
Whitwell Street paving and lining is complete and sidewalks are now open for public use.
A brief update for August 27:
· The contractor will be on site this Saturday, August 27th
Construction Updates:
- Building A
- Internal plumbing, fire protection, HVAC, and insulation are ongoing
- Exterior façade masonry is ongoing
- Drywall installation began on 8/22
- Building B
- Internal plumbing, fire protection, and insulation are ongoing
- Building C
- Foundation excavation is ongoing
- Building D
- Wood framing is ongoing and nearing completion
- Internal fire protection has begun
- Admin Building
- Exterior waterproofing and masonry restoration are ongoing
- Plumbing and Fire protection is ongoing
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.