Dear Neighbors:

Whitwell Street paving and lining is complete and sidewalks are now open for public use.

A brief update for August 27:

·         The contractor will be on site this Saturday, August 27th

Construction Updates:

  • Building A
    • Internal plumbing, fire protection, HVAC, and insulation are ongoing
    • Exterior façade masonry is ongoing
    • Drywall installation began on 8/22
  • Building B
    • Internal plumbing, fire protection, and insulation are ongoing
  • Building C
    • Foundation excavation is ongoing
  • Building D
    • Wood framing is ongoing and nearing completion
    • Internal fire protection has begun
  • Admin Building
    • Exterior waterproofing and masonry restoration are ongoing
    • Plumbing and Fire protection is ongoing

For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.

 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.