Dear Neighbors:
 
A brief update for July 30:
  • The contractor will be on site this Saturday, July 30th
 
Construction Updates:
  • Building A
    • Internal plumbing, fire protection, HVAC, and insulation are ongoing.
    • Window & door installation will be completed in the next two weeks.
    • Exterior façade masonry began 7/18/22.
  • Building B
    • Internal plumbing, fire protection, and insulation are ongoing.
    • Garage underground concrete is ongoing.
    • Window and door installation is ongoing.
  • Building C
    • Excess soil removal is nearing completion.
    • Foundation excavation to begin 8/8/22.
  • Building D
    • Wood framing is ongoing.
    • Admin Building
    • Exterior waterproofing and masonry restoration are ongoing.
    • Interior steel erection is nearing completion.
  • Whitwell Street
    • The sidewalk extension work is nearing completion
    • The site fence will be relocated by the end of the week. 
 
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.