Dear Neighbors:
A brief update for July 16:
- The contractor will be on site this Saturday, July 16th
- With the completion of the base layer of paving additional contractor parking is now available on-site
Construction Updates:
- Whitwell Street:
- Work to extend the sidewalks along Whitwell Street is underway. This includes temporary sidewalk detours and installation of temporary crosswalks
- New curbing is being set along Whitwell Street and is expected to be complete this week
- Sidewalk concrete placement will begin next week
- Building A:
- Mechanical, electrical, and plumbing work is ongoing.
- Insulation is underway
- Window installation is ongoing
- Building B:
- Roofing is expected to be complete in the next few days
- Mechanical, electrical, and plumbing work is ongoing
- Insulation is underway
- Garage utility installation is underway
- Window installation began this week
- Building C:
- Soil removal process to prepare for the excavation of Building C is ongoing
- Building D:
- Wood framing is ongoing
- Administration Building:
- Exterior waterproofing and masonry restoration continues
- Interior concrete slab cutting has been completed
- Restoration work continues
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.