Dear Neighbors:
A brief update for July 9:
  • The contractor will be on site this Saturday, July 9th
  • With the completion of the base layer of paving additional contractor parking is now available on-site.
 
Construction Updates:
  • Whitwell Street:
    • Work to extend the sidewalks along Whitwell Street is underway. This includes temporary sidewalk detours and installation of temporary crosswalks.
  • Building A:
    • Mechanical, electrical, and plumbing work is ongoing.
    • Insulation is underway.
    • Window installation is ongoing
  • Building B:
    • Wood framing is now complete
    • Roofing is underway
    • Mechanical, electrical, and plumbing work is ongoing.
    • Insulation is underway.
    • Garage utility installation is underway.
  • Building C:
    • Excavation for Building C is now expected to begin next week
  • Building D:
    • Wood framing is ongoing
  • Administration Building:
    • Masonry restoration continues
    • Interior concrete slab cutting will be completed next week
    • Restoration work continues
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.