Dear Neighbors:
A brief update for July 9:
- The contractor will be on site this Saturday, July 9th
- With the completion of the base layer of paving additional contractor parking is now available on-site.
Construction Updates:
- Whitwell Street:
- Work to extend the sidewalks along Whitwell Street is underway. This includes temporary sidewalk detours and installation of temporary crosswalks.
- Building A:
- Mechanical, electrical, and plumbing work is ongoing.
- Insulation is underway.
- Window installation is ongoing
- Building B:
- Wood framing is now complete
- Roofing is underway
- Mechanical, electrical, and plumbing work is ongoing.
- Insulation is underway.
- Garage utility installation is underway.
- Building C:
- Excavation for Building C is now expected to begin next week
- Building D:
- Wood framing is ongoing
- Administration Building:
- Masonry restoration continues
- Interior concrete slab cutting will be completed next week
- Restoration work continues
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.