Dear Neighbors:
 
A brief update for June 3-10:
  • The contractor will be on site this Saturday, June 4th
Construction Updates:
  • Whitwell Street:
    • Work to extend the sidewalks along Whitwell Street is underway. This includes temporary sidewalk detours and installation of temporary crosswalks. The construction fence was relocated to roughly the location of the existing shoulder and will remain there throughout the course of the work. The MBTA bus stop has been shifted down toward Adams Street near 80 Whitwell Street.
  • Building A:
    • Wood framing is expected to be complete by 6/7
    • Roofing is expected to begin the week of 6/13
    • Interior plumbing, fire protection, and insulation is ongoing
  • Building B:
    • Wood framing is ongoing
    • Interior plumbing and insulation are ongoing
    • Underground excavation and plumbing are ongoing
  • Building D:
    • Slab on deck rebar and concrete was completed on 5/27
    • Wood framing is now expected to begin the week of 6/6
  • Administration Building:
    • Exterior waterproofing and masonry are ongoing
    • Interior steel erection is ongoing
    • Restoration work is underway