Dear Neighbors:
 
A brief update for May 27- June 3:
  • The contractor will not be on site this Saturday, May 27th
  • The construction team will be observing Monday’s holiday
 
Construction Updates:
  • Whitwell Street:
    • Work to extend the sidewalks along Whitwell Street is underway. This includes temporary sidewalk detours and installation of temporary crosswalks. The construction fence was relocated to roughly the location of the existing shoulder and will remain there throughout the course of the work. 
    • We currently anticipate the work to be complete by 6/20/22. The fence line will then be pulled back in and the sidewalks will be reopened for pedestrian access. The MBTA bus stop will be shifted down toward Adams Street near 80 Whitwell Street
  • Building A:
    • Wood framing is expected to be complete by 6/7/22
    •  Interior plumbing, fire protection, and insulation is ongoing
  • Building B:
    • Wood framing is ongoing
    • Interior plumbing and insulation are ongoing
    • Underground excavation and plumbing are ongoing
  • Building D:
    • Metal deck installation was completed on 5/20
    • Slab on deck rebar and concrete is expected to be complete this week or early next week
    • Wood framing is expected to begin next week
  • Administration Building:
    • Interior backfill on the addition was completed on 5/20
    • Exterior waterproofing and masonry are ongoing
    • Interior steel erection is ongoing
    • Restoration work is underway