Dear Neighbors:
A note from the FoxRock team:
Our contractor, DellbrookJKS, has been contacting adjacent neighbors who have been impacted by the dust and mud onsite. Their team will be implementing measures to ensure that this is improved for the seasons ahead. Please reach out to us if there are any questions or comments.
A brief update for April 8-April 15:
- The contractor will be on site this Saturday, April 9th
Construction Updates:
- Whitwell Street:
- Work to extend the sidewalks along Whitwell Street in front of the project began on 4/5/22. This includes temporary sidewalk detours and installation of temporary crosswalks. The construction fence will be relocated to roughly the location of the existing shoulder and will remain there throughout the course of the work. We currently anticipate the work to be complete by 6/20/22. The fence line will then be pulled back in and the sidewalks will be reopened for pedestrian access. The MBTA bus stop will be shifted down toward Adams Street near 80 Whitwell Street.
- Building A:
- Wood framing began on 3/7 and is ongoing
- Building B:
- Wood framing began on 3/17 and is ongoing
- Building D:
- Structural steel erection began on 3/30 and is ongoing
- Administration Building:
- Underground plumbing was completed on 4/1
- Excavation for the Admin building addition is expected to begin on 4/14
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.
Thank You,
The FoxRock Properties Team