Dear Neighbors:
 

A brief update for March 25th – April 1:

  • The contractor will be on site this Saturday, March 26th

Construction Updates:

Building B:

  • Ground floor slab rebar and concrete placement is ongoing
  • Wood framing began on 3/17

Building D:

  • Foundation work is complete
  • Initial backfilling and waterproofing was completed on 3/18
  • Elevator shaft masonry work is underway and is expected to be complete in the next few days
  • Structural steel erection is expected to begin next week

Building A:

  • Wood framing began on 3/7 and is ongoing

Administration Building:

  • Underground utility connections were completed on 3/18
  • Excavation for the Admin building addition is expected to begin next week
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.

Thank You,

The FoxRock Properties Team