Dear Neighbors:
A brief update for March 11th-18th:
  • The contractor will not be on site this Saturday, March 12th
Construction Updates:
  • Building B:
    • Steel erection is complete
    • Metal decking installation is expected to be complete this week
    • Ground floor slab rebar and concrete placement is ongoing
    • Wood framing is expected to begin next week
  • Building D:
    • Foundation work and rebar was completed last week
    • Foundation backfilling and waterproofing is ongoing
    • Elevator masonry is expected to begin next week
  • Building A:
    • Wood framing began 3/7
    • Underground plumbing was completed last week
    • Ground floor slab rebar and concrete is expected to be complete next week
    • Elevator shaft masonry was completed last week
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.

 

 

Thank You,

The FoxRock Properties Team