Dear Neighbors:
 
A brief update for March 4th-11th:
  • The contractor will not be on site this Saturday, March 5th
Construction Updates:
  • Building B:
    • Steel erection is complete
    • Metal decking installation is still ongoing
    • Ground floor slab rebar and concrete began last week
  • Building D:
    • Foundation work is expected to be complete in the next few days
    • Steel erection is expected to start in the next few weeks
  • Building A:
    • Underground plumbing should be complete in the next few days
    • Ground floor concrete placing
    • Elevator shaft masonry are all ongoing
  • Wood framing for buildings A and B is still on track to begin in the next week
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.

 

 

Thank You,

The FoxRock Properties Team

FoxRockProperties.com