Dear Neighbors:
A brief update for February 25th – March 4th:
- The contractor will be on site this Saturday, February 26th
Construction Updates:
- Building B steel erection is complete, metal decking installation is still ongoing
- Building D foundation work is expected to be completed 3/3
- Building A underground plumbing, ground floor concrete placing, and elevator masonry are all ongoing
- Wood framing for buildings A and B is still on track to begin in the next few weeks
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.