Dear Neighbors:
A brief update for February 18th-25th:
  • The above site plan shows the location of each of the buildings on the Ashlar Park site
  • The contractor will not be on site this Saturday, February 19th
Construction Updates:
  • Building B steel erection is complete, metal decking installation is ongoing
  • Building D foundation work is ongoing, footings are 90% complete
  • Building A underground plumbing is ongoing. Ground floor concrete placing began on 2/14 and elevator masonry will begin in the next few days
  • Wood framing for buildings A and B is still on track to begin in the next few weeks
  • Administration Building underground plumbing installation is ongoing; preparation for concrete slab cutting and supplemental steel began on 2/14
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 