Dear Neighbors:
A brief update for December 24 – January 1:
  • There will be no contractor on site this Saturday, December 25th or next Saturday, January 1st
  • The site will be closing early on Friday, December 24th
  • The USPS has moved the mailbox that was in front of 114 Whitwell Street to 121 Whitwell Street (the yellow building across the street)
Construction Updates:
  • Building B steel erection began 12/15
  • Building D foundation excavation and foundation work is ongoing
  • Building A excavation is now complete; concrete pouring is about 40% complete and expected to be fully complete at the end of next week
  • Wood framing for buildings A and B is expected to begin in February
  • Retaining wall work has started along the Western property line
  • Slab prep is underway in the Administration Building for below grade utilities
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.

 

 

Thank You,

The FoxRock Properties Team

FoxRockProperties.com