Dear Neighbors:
A brief update for December 24 – January 1:
- There will be no contractor on site this Saturday, December 25th or next Saturday, January 1st
- The site will be closing early on Friday, December 24th
- The USPS has moved the mailbox that was in front of 114 Whitwell Street to 121 Whitwell Street (the yellow building across the street)
Construction Updates:
- Building B steel erection began 12/15
- Building D foundation excavation and foundation work is ongoing
- Building A excavation is now complete; concrete pouring is about 40% complete and expected to be fully complete at the end of next week
- Wood framing for buildings A and B is expected to begin in February
- Retaining wall work has started along the Western property line
- Slab prep is underway in the Administration Building for below grade utilities
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.
Thank You,
The FoxRock Properties Team