Dear Neighbors:
A brief update for December 10 – December 17:
- The contractor will be on site Saturday, December 11th
- A new 8-foot fence will be installed around the entire construction site starting next week
- Building B foundation interior piers, footings and foundations were completed last week
- Building D foundation excavation began on 11/3 and is ongoing, foundation work has now begun
- Building A excavation is ongoing; footings and foundation began this week
- The team is preparing the Administration Building slab for underground plumbing
- Saturday work will continue on a regular basis throughout the duration of the project
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.
Thank You,
The FoxRock Properties Team