A brief update for December 3 – December 10:
  • The contractor will be on site Saturday, December 4th
  • Building B foundation interior piers are expected to be completed this week
  • Foundation work for Building B footings and foundations is ongoing with completion anticipated for 12/8
  • Building D foundation excavation began on 11/3 and is ongoing, foundation work is expected to begin 12/9
  • Building A excavation has begun
  • Saturday work will continue on a regular basis throughout the duration of the project
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 