A brief update for December 3 – December 10:
- The contractor will be on site Saturday, December 4th
- Building B foundation interior piers are expected to be completed this week
- Foundation work for Building B footings and foundations is ongoing with completion anticipated for 12/8
- Building D foundation excavation began on 11/3 and is ongoing, foundation work is expected to begin 12/9
- Building A excavation has begun
- Saturday work will continue on a regular basis throughout the duration of the project
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.