A brief update for November 26 – December 3:
  • The team will be observing the holiday on Thursday, November 25th and will not be on site
  • A small maintenance team will be on site Saturday, November 27th
  • A portion of the loop road and parking lot was paved last week
  • Interior demolition at the Administration Building is nearing completion
  • Building B foundation interior piers are expected to be complete by 11/30
  • Foundation work for Building B footings and foundations is ongoing
  • Building D foundation excavation began on 11/3 and is ongoing, rebar is arriving 11/30
  • Building A excavation has begun
  • Saturday work will continue on a regular basis throughout the duration of the project
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
 
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
 
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.

 

 

Thank You,

The FoxRock Properties Team