We’ve reached the point in the project where we will be extending construction activities to Saturdays, which is expected to continue on a regular basis throughout the duration of the project.
A brief update for Saturday, October 9:
- The construction team will be on-site and working this Saturday, October 9th
- Building B foundation excavation is expected to be complete by October 15th
- Building B interior piers began at the end of last month and foundation walls are ongoing
- Building D foundation excavation is expected to begin the week of October 11th
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372. Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.