Dear Neighbors,
A brief project update for the week of August 9th:
- The demolition phase of the project is now complete as scheduled
- Sitework will continue through the summer and into the fall
- Foundation work will begin later this summer and continue through fall
- Thank you to everyone who has reached out over the past few months – as we begin the construction phase of the project, please continue to use the channels of communication to let us know of any questions or concerns
For construction-related questions or concerns, please call our “construction hotline” at (617) 890-9430.
As always, if you or any of the members of the community have any questions or concerns, please don’t hesitate to reach out to us at ashlarpark@foxrockquincy.com or text 617-890-6372.
Please visit our website, www.114whitwell.com, to review previous updates, to find construction-related contact information and subscribe to these emails.
Thank You,
The FoxRock Properties Team